Montclair Water Bureau and Sewer Utility
54 Watchung Avenue
Montclair, NJ 07042
Gary Obszarny, Director
E-mail:
This e-mail address is being protected from spambots. You need JavaScript enabled to view it
Phone: 973-744-4600
Hours: Monday - Friday, 8:30 a.m.-4:30 p.m.
PLEASE NOTE - for water billing questions call: 973-509-4924 / 4925
Water/Sewer payments must be mailed to: 205 Claremont Avenue, Montclair, NJ 07042
|
|
Please note: work is dependent on weather
| Date |
Work Area |
Description |
| Tuesday, 07-26 |
Yantacaw Brook Road |
Mill and prep full length |
| |
Alexander Road |
Mill half length |
| Wednesday, 07-27 |
Yantacaw Brook Road |
Asphalt pave f ull length |
| |
Alexander Road |
Finish mill and prep |
| |
Grove Street |
Mill and prep |
| Thursday, 07-28 |
Alexander Road |
Asphalt pave full length |
| Friday, 07-29 |
Grove Street |
Asphalt pave |
| |
ALL |
Stripe |
|
|
|
This week (week of July 18) crews will be grouting sewer lines and performing sewer line video inspections on Alexander Avenue. There may be minor traffic issues associated with the work (two trucks in the road) but road closures are not likely.
During the week of July 25, work crews will be cleaning and performing video inspections of sewer laterals on Alexander Avenue; they will also be coordinating duties with County trench restoration crews. This may result in minor traffic issues during the week (two trucks in the road), including the possibility of lane closures.
Yantacaw Brook Road will be milled and paved from the July 27-29. Traffic will need to be diverted during milling and paving.
During the weeks of August 1 and August 8 sewer laterals will be relined on Alexander Avenue. While this work is taking place, residents will be notified that they cannot use their sewer lines for approximately two hours while the lining process takes place. Only two laterals will be done per day. Minor traffic issues are anticipated, however residents must keep in mind that approximately 20 laterals must be relined.
In the event of major rainfall, paving and sewer work will be canceled and the schedule will be extended. For questions, please contact the Montclair Sewer Utility at 973-744-4600. |
|
Download 2010 Water Quality Report
The Montclair Water Bureau is once again proud to present our annual water quality report covering all testing performed between January 1 and December 31, 2010. As in years past, we are committed to delivering the best-quality drinking water possible. To that end, we remain vigilant in meeting the challenges of new regulations, source water protection, water conservation, and community outreach and education while continuing to serve the needs of all of our water users. Thank you for allowing us to continue providing you and your family with quality drinking water.
We encourage you to share your thoughts with us on the information contained in this report. Should you ever have any questions or concerns, we are always available to assist you. Please contact the Water Bureau with any questions, comments or concerns: 973-744-4600. |
|
|
Work on a manhole for tying in the existing sewer line to the new 18” sewer line will begin Tuesday, May 5 and will be completed on Wednesday, May 11. Download the traffic control plan for this portion of the Montclair/MSU sewer project work. |
|
Montclair Township-MSU Sewer Project: Planned Work Activity
Traffic patterns will be affected in parts of Upper Montclair
The Montclair Township Sewer Utility has provided a schedule of work on the Township-Montclair State University sewer project planned for the period through April 25.
Schedules for work Crews 1, 2 and 3 are posted below. Maps of sewer work and traffic re-routing can be downloaded here. All road disruptions have been discussed and coordinated with the Montclair Police Department. The maps show the blocks where traffic will be affected during project construction.
The project contractor anticipates that sewer service interruptions should affect no more than two residences at a time. Twenty-four-hour advance notifications will be made to the individual addresses that will be directly affected by service interruptions. In addition, block-by-block meetings will be scheduled to inform residents about the work and work schedules for their areas.
Street excavations will be closed up at the end of each day. Please note: the work schedule is subject to change, depending on existing conditions and weather.
Montclair Township Sewer Improvements Traffic Management Work Plan
CREW 1 (Alexander Road)
Date |
Description |
Main Road Work |
Between |
And |
Start |
Finish |
Police |
04/18/11 |
Installing 18" sanitary towards MH 100A |
Alexander Road |
MH 101 |
MH 100A |
7:00 AM |
4:00 PM |
3 |
04/19/11 |
Installing 18" sanitary towards MH 100A |
Alexander Road |
MH 101 |
MH 100A |
7:00 AM |
4:00 PM |
3 |
04/20/11 |
Install 12" toward MH 37 |
Alexander Road |
MH 100A |
MH 37 |
7:00 AM |
4:00 PM |
3 |
04/21/11 |
Install 12" toward and tie intoMH 37 |
Alexander Road |
MH 100A |
MH 37 |
7:00 AM |
4:00 PM |
3 |
04/22/11 |
Field build MH 38 & install 12: sanitary & set MH 38A |
Alexander Road |
MH 38 |
MH 38A |
7:00 AM |
4:00 PM |
3 |
| 04/23/11 |
|
|
|
|
|
|
|
| 04/24/11 |
|
|
|
|
|
|
|
| 04/25/11 |
Last sewer lateral; miscellaneous clean-up |
Yantacaw Brook Rd |
|
|
7:00 AM |
4:00 PM |
|
NOTE: After turning over new system to Township/MSU -- 1-2 days to make switch over of existing flow at MH
CREW 2 (Alexander Road)
Date |
Description |
Main Road Work |
Between |
And |
Start |
Finish |
Police |
04/18/11 |
Install 12" sanitary towards MH 41 |
Alexander Rd |
MH 40 |
MH 41 |
7:00 AM |
4:00 PM |
- |
04/19/11 |
Install 12" sanitary towards MH 41 |
Alexander Rd |
MH 40 |
MH 41 |
7:00 AM |
4:00 PM |
- |
04/20/11 |
Install 12" sanitary towards MH 41 |
Alexander Rd |
MH 40 |
MH 41 |
7:00 AM |
4:00 PM |
- |
04/21/11 |
Install 12" sanitary towards & tie-in MH 41 |
Alexander Rd |
MH 40 |
MH 41 |
7:00 AM |
4:00 PM |
- |
04/22/11 |
Finisi loose ends; finish testing if needed |
Alexander Rd |
MH 40 |
MH 41 |
7:00 AM |
4:00 PM |
- |
04/23/11 |
|
|
|
|
|
|
- |
04/24/11 |
|
|
|
|
|
|
- |
| 04/25/11 |
Miscelaneous odds & ends |
|
|
|
|
|
|
NOTE: After turning over new system to Township/MSU -- 1-2 days to make switch over of existing flow at MH B00-48-28 to MH 100A
Crew 3 (Yantaw Brook Road)
Date |
Description |
Main Road Work |
Between |
And |
Start |
Finish |
Police |
04/18/11 |
Grading, topsoil, seeding, mulching, clean-up |
Yantacaw Brook Road |
Woodmont Ave |
Club Rd |
7:00 AM |
3:30 PM |
- |
04/19/11 |
Grading, topsoil, seeding, mulching, clean-up |
Yantacaw Brook Road |
Woodmont Ave |
Club Rd |
7:00 AM |
3:30 PM |
- |
04/20/11 |
Finish clean-up at park |
Yantacaw Brook Road |
Woodmont Ave |
Club Rd |
7:00 AM |
3:30 PM |
- |
Progressive Lining
Date |
Description |
Main Road Work |
Between |
And |
Start |
Finish |
Police |
04/18/11 |
|
|
|
|
|
|
- |
04/19/11 |
Taking care of punch list items that need to be done |
Yantacaw Brook Park |
MH 11 |
MH 9 |
7:00 AM |
4:00 PM |
- |
04/20/11 |
Finish clean-up & repairing equipment, pumps & hoses |
Yantacaw Brook Park |
MH 11 |
MH 9 |
7:00 AM |
4:00 PM |
- |
04/21/11 |
Taking care of punch list items that need to be done |
Yantacaw Brook Park |
MH 11 |
MH 2 |
7:00 AM |
4:00 PM |
2 |
|
|
|
|
|