Skip to content
Increase font size Decrease font size Default font size

Montclair Township

Water Bureau/Sewer Utility

Montclair Water Bureau and Sewer Utility
54 Watchung Avenue
Montclair, NJ 07042

Gary Obszarny, Director
E-mail: This e-mail address is being protected from spambots. You need JavaScript enabled to view it
Phone: 973-744-4600

Hours: Monday - Friday, 8:30 a.m.-4:30 p.m.

PLEASE NOTE - for water billing questions call: 973-509-4924 / 4925

Water/Sewer payments must be mailed to: 205 Claremont Avenue, Montclair, NJ 07042



Montclair Township-MSU Sewer Project: Planned Work Activity through July 29 PDF Print E-mail

Please note: work is dependent on weather

Date Work Area Description
Tuesday, 07-26 Yantacaw Brook Road Mill and prep full length
  Alexander Road Mill half length
Wednesday, 07-27 Yantacaw Brook Road Asphalt pave f ull length
  Alexander Road Finish mill and prep
  Grove Street Mill and prep
Thursday, 07-28 Alexander Road Asphalt pave full length
Friday, 07-29 Grove Street Asphalt pave
  ALL Stripe
 
NOTICE FROM THE MONTCLAIR SEWER UTILITY PDF Print E-mail

This week (week of July 18) crews will be grouting sewer lines and performing sewer line video inspections on Alexander Avenue. There may be minor traffic issues associated with the work (two trucks in the road) but road closures are not likely.

During the week of July 25, work crews will be cleaning and performing video inspections of sewer laterals on Alexander Avenue; they will also be coordinating duties with County trench restoration crews. This may result in minor traffic issues during the week (two trucks in the road), including the possibility of lane closures.

Yantacaw Brook Road will be milled and paved from the July 27-29. Traffic will need to be diverted during milling and paving.

During the weeks of August 1 and August 8 sewer laterals will be relined on Alexander Avenue.  While this work is taking place, residents will be notified that they cannot use their sewer lines for approximately two hours while the lining process takes place. Only two laterals will be done per day. Minor traffic issues are anticipated, however residents must keep in mind that approximately 20 laterals must be relined.

In the event of major rainfall, paving and sewer work will be canceled and the schedule will be extended. For questions, please contact the Montclair Sewer Utility at 973-744-4600.

 
Montclair/MSU Sanitary Sewer Traffic Control Plans for May 10-11 PDF Print E-mail

Work on a manhole for tying in the existing sewer line to the new 18” sewer line will begin Tuesday, May 5 and will be completed on Wednesday, May 11. Download the traffic control plan for this portion of the Montclair/MSU sewer project work.

 
Montclair/MSU Sewer Project Update Through April 25 PDF Print E-mail

Montclair Township-MSU Sewer Project: Planned Work Activity

Traffic patterns will be affected in parts of Upper Montclair

The Montclair Township Sewer Utility has provided a schedule of work on the Township-Montclair State University sewer project planned for the period through April 25.

Schedules for work Crews 1, 2 and 3 are posted below. Maps of sewer work and traffic re-routing can be downloaded here. All road disruptions have been discussed and coordinated with the Montclair Police Department. The maps show the blocks where traffic will be affected during project construction.

The project contractor anticipates that sewer service interruptions should affect no more than two residences at a time. Twenty-four-hour advance notifications will be made to the individual addresses that will be directly affected by service interruptions. In addition, block-by-block meetings will be scheduled to inform residents about the work and work schedules for their areas.

Street excavations will be closed up at the end of each day. Please note: the work schedule is subject to change, depending on existing conditions and weather.

Montclair Township Sewer Improvements Traffic Management Work Plan

CREW 1 (Alexander Road)

Date

Description

Main Road Work

Between

And

Start

Finish

Police

04/18/11

Installing 18" sanitary towards MH 100A

Alexander Road

MH 101

MH 100A

7:00 AM

4:00 PM

3

04/19/11

Installing 18" sanitary towards MH 100A

Alexander Road

MH 101

MH 100A

7:00 AM

4:00 PM

3

04/20/11

Install 12" toward MH 37

Alexander Road

MH 100A

MH 37

7:00 AM

4:00 PM

3

04/21/11

Install 12" toward and tie intoMH 37

Alexander Road

MH 100A

MH 37

7:00 AM

4:00 PM

3

04/22/11

Field build MH 38 & install 12: sanitary & set MH 38A

Alexander Road

MH 38

MH 38A

7:00 AM

4:00 PM

3

04/23/11              
04/24/11              
04/25/11 Last sewer lateral; miscellaneous clean-up Yantacaw Brook Rd     7:00 AM 4:00 PM  

NOTE: After turning over new system to Township/MSU -- 1-2 days to make switch over of existing flow at MH

CREW 2 (Alexander Road)

Date

Description

Main Road Work

Between

And

Start

Finish

Police

04/18/11

Install 12" sanitary towards MH 41

Alexander Rd

MH 40

MH 41

7:00 AM

4:00 PM

-

04/19/11

Install 12" sanitary towards MH 41

Alexander Rd

MH 40

MH 41

7:00 AM

4:00 PM

-

04/20/11

Install 12" sanitary towards MH 41

Alexander Rd

MH 40

MH 41

7:00 AM

4:00 PM

-

04/21/11

Install 12" sanitary towards & tie-in MH 41

Alexander Rd

MH 40

MH 41

7:00 AM

4:00 PM

-

04/22/11

Finisi loose ends; finish testing if needed

Alexander Rd

MH 40

MH 41

7:00 AM

4:00 PM

-

04/23/11

-

04/24/11

-

04/25/11 Miscelaneous odds & ends            

NOTE: After turning over new system to Township/MSU -- 1-2 days to make switch over of existing flow at MH B00-48-28 to MH 100A

Crew 3 (Yantaw Brook Road)

Date

Description

Main Road Work

Between

And

Start

Finish

Police

04/18/11

Grading, topsoil, seeding, mulching, clean-up

Yantacaw Brook Road

Woodmont Ave

Club Rd

7:00 AM

3:30 PM

-

04/19/11

Grading, topsoil, seeding, mulching, clean-up

Yantacaw Brook Road

Woodmont Ave

Club Rd

7:00 AM

3:30 PM

-

04/20/11

Finish clean-up at park

Yantacaw Brook Road

Woodmont Ave

Club Rd

7:00 AM

3:30 PM

-

Progressive Lining

Date

Description

Main Road Work

Between

And

Start

Finish

Police

04/18/11

 

 

 

 

 

 

-

04/19/11

Taking care of punch list items that need to be done

Yantacaw Brook Park

MH 11

MH 9

7:00 AM

4:00 PM

-

04/20/11

Finish clean-up & repairing equipment, pumps & hoses

Yantacaw Brook Park

MH 11

MH 9

7:00 AM

4:00 PM

-

04/21/11

Taking care of punch list items that need to be done

Yantacaw Brook Park

MH 11

MH 2

7:00 AM

4:00 PM

2

 
Montclair/MSU Sewer Project Update Through April 17 PDF Print E-mail

Montclair Township-MSU Sewer Project: Planned Work Activity

Traffic patterns will be affected in parts of Upper Montclair

The Montclair Township Sewer Utility has provided a schedule of work on the Township-Montclair State University sewer project planned for the period through April 22.

Schedules for work Crews 1, 2 and 3 are posted below. Maps of sewer work and traffic re-routing can be downloaded here. All road disruptions have been discussed and coordinated with the Montclair Police Department. The maps show the blocks where traffic will be affected during project construction.

The project contractor anticipates that sewer service interruptions should affect no more than two residences at a time. Twenty-four-hour advance notifications will be made to the individual addresses that will be directly affected by service interruptions. In addition, block-by-block meetings will be scheduled to inform residents about the work and work schedules for their areas.

Street excavations will be closed up at the end of each day. Please note: the work schedule is subject to change, depending on existing conditions and weather.

Montclair Township Sewer Improvements
Traffic Management Work Plan

YANTACAW BROOK ROAD

Date

Description

Main Road Work

Between

And

Start

Finish

Police

04/04/11

Installing 18" sanitary towards MH 100A

Yantacaw Brook Road

MH 102

MH 101

7:00 AM

4:00 PM

2

04/05/11

Installing 18" sanitary towards MH 100A

Yantacaw Brook Road

MH 102

MH 101

7:00 AM

4:00 PM

2

04/06/11

Installing 18" sanitary towards MH 100A

Yantacaw Brook Road

MH 102

MH 101

7:00 AM

4:00 PM

2

04/07/11

Installing MH 102 going toward MH 101

Yantacaw Brook Road

MH 102

MH 101

7:00 AM

4:00 PM

2

04/08/11

Installing 18" sanitary towards MH 101

Yantacaw Brook Road

MH 102

MH 101

7:00 AM

4:00 PM

2

04/09/11

-

04/10/11

-

04/11/11

Installing 18" sanitary towards MH 101

Yantacaw Brook Road

MH 102

MH 101

7:00 AM

4:00 PM

2

04/12/11

Setting MH 101; going towards MH 100A

Yantacaw Brook Road

MH 101

MH 100A

7:00 AM

4:00 PM

2

04/13/11 Installing 18" sanitary towards MH 100A Yantacaw Brook Road MH 101 MH 100A 7:00 AM 4:00 PM 2
04/14/11 Installing 18" sanitary towards MH 100A Yantacaw Brook Road MH 101 MH 100A 7:00 AM 4:00 PM 2
04/15/11 Installing 18" sanitary towards MH 100A Yantacaw Brook Road MH 101 MH 100A 7:00 AM 4:00 PM 2
04/16/11 -
04/17/11 -

Montclair Township Sewer Improvements
Traffic Management Work Plan

CREW 1 (Alexander Road)

Date

Description

Main Road Work

Between

And

Start

Finish

Police

04/18/11

Installing 18" sanitary towards MH 100A

Alexander Road

MH 101

MH 100A

7:00 AM

4:00 PM

2

04/19/11

Installing 18" sanitary towards MH 100A

Alexander Road

MH 101

MH 100A

7:00 AM

4:00 PM

2

04/20/11

Setting MH 100A & MH 800-48-28

Alexander Road

MH 101

MH 800-48-28

7:00 AM

4:00 PM

2

04/21/11

Finish MH 48-28; install 12: toward MH 37

Alexander Road

MH 100A

MH 37

7:00 AM

4:00 PM

2

04/22/11

Tie-into MH 37

Alexander Road

MH 37

 

7:00 AM

4:00 PM

2

Montclair Township Sewer Improvements
Traffic Management Work Plan

CREW 2 (Alexander Road)

Date

Description

Main Road Work

Between

And

Start

Finish

Police

04/04/11

Install 12" sanitary towards MH 39

Alexander Rd

MH 38

MH 39

7:00 AM

4:00 PM

2

04/05/11

Install 12" sanitary towards MH 40

Alexander Rd

MH 39

MH 40

7:00 AM

4:00 PM

2

04/06/11

Install 12" sanitary towards MH 40

Alexander Rd

MH 39

MH 40

7:00 AM

4:00 PM

2

04/07/11

Install 12" sanitary towards MH 40

Alexander Rd

MH 39

MH 40

7:00 AM

4:00 PM

2

04/08/11

Install 12" sanitary towards MH 41

Alexander Rd

MH 40

MH 41

7:00 AM

4:00 PM

2

04/09/11

-

04/10/11

-

04/11/11

Install 12" sanitary towards MH 41

Alexander Rd

MH 40

MH 41

7:00 AM

4:00 PM

-

04/12/11

Install 12" sanitary towards MH 41

Alexander Rd

MH 40

MH 41

7:00 AM

4:00 PM

-

04/13/11

Install 12" sanitary towards MH 41

Alexander Rd

MH 40

MH 41

7:00 AM

4:00 PM

-

04/14/11

Install 12" sanitary towards MH 41

Alexander Rd

MH 40

MH 41

7:00 AM

4:00 PM

-

04/15/11

Install 12" sanitary towards MH 41

Alexander Rd

MH 41

 

7:00 AM

4:00 PM

-

04/16/11

-

04/17/11

-

Montclair Township Sewer Improvements
Traffic Management Work Plan

Crew #3 (Testing)

Date

Description

Main Road Work

Between

And

Start

Finish

Police

04/14/11

Testing and mason work as required

Yantacaw Brook Road

MH 108

MH 105

7:00 AM

3:30 PM

-

04/15/11

Testing and mason work as required

Yantacaw Brook Road

MH 105

MH 103

7:00 AM

3:30 PM

-

04/16/11

Testing and mason work as required

Yantacaw Brook Road

MH 13

MH 41

7:00 AM

3:30 PM

-

04/17/11

Testing and mason work as required

Yantacaw Brook Road

MH 37

MH 39

7:00 AM

3:30 PM

-

04/18/11

Testing and mason work as required

Yantacaw Brook Road

MH 39

MH 40

7:00 AM

3:30 PM

-

Montclair Township Sewer Improvements
Traffic Management Work Plan

In situe form (Lining Contractor)

Date

Description

Main Road Work

Between

And

Start

Finish

Police

04/04/11

Lining & curing 12" sanitary

Alexander Rd

MH 800-48-28

MH 38

7:00 AM

7:00 PM

-

04/05/11

Lining & curing 12" sanitary

Alexander Rd

MH 38

MH 41

7:00 AM

7:00 PM

-

04/06/11

Lining & curing 12" sanitary

Alexander Rd

MH 41
MH 46

MH 44
MH 47

7:00 AM

7:00 PM

2

04/07/11

Lining & curing 12" sanitary

Alexander Rd

MH 47

MH 49

7:00 AM

7:00 PM

2

04/08/11

Lining & curing 12" sanitary

Alexander Rd

MH 52

MH 54

7:00 AM

7:00 PM

2

04/09/11

-

04/10/11

-

04/11/11

Setting up by-pass for 21" lining

Alexander Rd

MH 9

MH 3

7:00 AM

4:00 PM

-

04/12/11

Finish setting up by-pass; do a test run

Alexander Rd

MH 9

MH 3

7:00 AM

4:00 PM

-

04/13/11

Line & cure 21" lining

Alexander Rd

MH 8

MH 4

7:00 AM

7:00 PM

2

04/14/11

Tear down by-pass & replace equipment (pumps)

Alexander Rd

MH 9

MH 3

7:00 AM

4:00 PM

-

04/15/11

Line & cure sanitary 8"

Alexander Rd

MH 51

MH 52

7:00 AM

4:00 PM

2

04/16/11

-

04/17/11

-

 
<< Start < Prev 1 2 3 4 5 Next > End >>

Page 2 of 5