Road Closure Information

Road Closure Information
Road Closure Information

Police detail schedule for August 16:

  • Edgemont Rd & Parkway (DCS road work)
  • Virginia Ave & High St (DCS road work)
  • N Fullerton Ave & Bloomfield Ave (construction)

Street Improvement Projects

Project Start: on or about Thursday, August 11, 2022, weather permitting

Bellevue Avenue from Bellegrove Drive to Woodmount Road (milling and paving). The project is expected to take approximately three to ten days to complete. During this construction period the street will be closed at various times throughout the duration of this project.

Project Start: on or about Thursday, August 11, 2022, weather permitting

North Mountain Avenue from Bellevue Avenue to the railroad tracks (milling and paving). The project is expected to take approximately three to ten days to complete. During this construction period the street will be closed at various times throughout the duration of this project.

Project Start: on or about Thursday, August 11, 2022, weather permitting

Bellevue Avenue from Valley Road to Northview Avenue (milling and paving). The project is expected to take approximately three to ten days to complete. During this construction period the street will be closed at various times throughout the duration of this project. 

Project Start: on or about Wednesday, August 10, 2022, weather permitting

Erwin Park Road from Holland Terrace to Midland Avenue (milling and paving). The project is expected to take approximately three to ten days to complete. During this construction period the street will be closed at various times throughout the duration of this project. 

Project Start: on or about Wednesday, August 10, 2022, weather permitting

Vera Place, Valley Road to Midland Avenue (milling and paving). The project is expected to take approximately three to ten days to complete. During this construction period the street will be closed at various times throughout the duration of this project. 

Project Start: on or about Tuesday, August 9, 2022, weather permitting

Walden Place (milling and paving). The project is expected to take approximately three to ten days to complete. During this construction period the street will be closed at various times throughout the duration of this project. 

Project Start: on or about Tuesday, August 9, 2022, weather permitting

  • Orange Road from Plymouth Street to Hillside Avenue (milling and paving). The project is expected to take approximately three to ten days to complete. During this construction period the street will be closed at various times throughout the duration of this project.

Project Start: on or about Tuesday, August 9, 2022, weather permitting

  • Lloyd Road from Bloomfield Avenue to Hoberg Place (milling and paving). The project is expected to take approximately three to ten days to complete. During this construction period the street will be closed at various times throughout the duration of this project.

Project Start: on or about Monday, August 8, 2022, weather permitting

  • Monroe Place  from Willowdale Avenue to Maple Avenue (milling and paving). The project is expected to take approximately three to ten days to complete. During this construction period the street will be closed at various times throughout the duration of this project. 

Project Start: on or about Monday, August 8, 2022, weather permitting

  • High Street from Cedar Road to West Orange border  (milling and paving). The project is expected to take approximately three to ten days to complete. During this construction period the street will be closed at various times throughout the duration of this project 

Curbing

No parking will be allowed on the street during the day while construction is in progress. The street may also be closed to traffic at various times during the day. If you must use your vehicle(s) during the day; it should be removed from your driveway and parked on a side street by 7:00 a.m.

Milling

The roadway will be open to traffic once milling operations and all cleanup has been completed. Expect delays due to the contractor’s activity if driving through the work area. Once milling has been completed, please use caution while driving or walking in these areas as the manholes will be raised. Paving will be completed within 5 to 7 days.

Paving

The roadway will remain closed to traffic for 4 to 6 hours after paving while the asphalt cools. No vehicles will be permitted on the roadway until the barricades are removed.

Police officers will be directing traffic during the milling and paving operations.


PSE&G project information go to:

nj.pseg.com/inthecommunity/constructioninyourtown